When a picking is created from a purchase order of a supplier, the lead
|
|
time used to calculate the scheduled date is computed in natural days. At the
|
|
same time, when a purchase order is created due to a a procurement
|
|
evaluation, its order date is also computed considering the lead time in
|
|
natural days. THis module adds the possibility of expressing the lead time
|
|
of a vendor in his own calendar. This way, the order dates of purchase
|
|
orders and the scheduled dates of receipts will only take into account the
|
|
supplier working days.
|