When a picking is created out of a procurement evaluation (from an orderpoint, MTO,...) the calendar is considered in the computation of the expected date of the picking and moves. For example, if it takes 1 day to execute a stock transfer from another warehouse and it is Monday, the picking to resupply will be created with expected start date on the previous Friday, if the warehouse operates under a Mo-Fri working calendar.